# Activity Description Unit Total Qty Done Qty Rate Budget Earned Start Finish Act.
expand_more layersFIRE PROTECTION SERVICES $473,917.89 $0.00 15-Apr-26 15-Nov-26
1 Fire Sprinkler Installation(L2-L12) LM 7,960.00 0.00 34.473 $274,405.08 $0.00 15-Apr-26 15-Sep-26
delete
2 Emergency And Fire Signage: LM 1,967.00 0.00 101.430 $199,512.81 $0.00 01-Sep-26 15-Nov-26
delete
Subtotal — FIRE PROTECTION SERVICES $473,917.89 $0.00
expand_more layersICT & FLS $540,856.96 $0.00 01-May-26 30-Sep-26
1 ICT & FLS LM 120,727.00 0.00 4.480 $540,856.96 $0.00 01-May-26 30-Sep-26
delete
Subtotal — ICT & FLS $540,856.96 $0.00
Total Project Valuation $1,014,774.85 $0.00